The program included rectifying the large trip hazard between Westfield & Council delineation and provide a more consistent profile.
As this area is a very busy thoroughfare, work was required to be commenced at 7:00pm and completed by 5:00am the following day.
The repair program required for site specific induction request for all crew members during the period 5:30-6:30pm (prior to the 7:00pm start).
Whilst time was short we covered establishment for all equipment & crew, installation of temporary worksite lighting, profiling excavation of existing dilapidated driveway asphalt inclusive of all ground engaging tools, cartage and disposal of all materials.
Prior to the 5:00am finish the area was cleaned up via bobcat broom.
Also required for this program was the application & supply of the CRS 170-60 Emulsion Track Coat to the newly prepared driveway floors and laying of the above nominated asphalt products to AS2150.
For the past 3 years we have exclusively used Craftwork Project Management for our interior and exterior surfaces. In that time we have been extremely happy with their clean, friendly and professional approach to our projects. Being a busy hotel Craftwork painters have worked closely with us in relation to rooms availability, painting requirements and technical expertise. There knowledge of hotel requirements has been a benefit to our operation, as they fully understand our business and therefore our requirements when it comes to guest, staff and time line requests. We are totally happy with all aspects of Craftwork, from there on site visits, product selection, to substrate preparation, final coat, too the signing off on the completed project and would recommend them to any business. The dedication from all Craftwork employees is exemplary, and other companies should take note of this.